What is a DNO Application?
- /Blogs
- /What is a DNO Application?
A DNO application is a request to connect your solar panel or battery system to the grid. Here, we explain who handles it, why you need it and how it works.
If you're planning to install solar panels or battery storage, you may hear your installer mention a DNO application. It's an important part of getting your system connected safely to the electricity network, but the process can sound more complicated than it needs to be.
The good news is that you usually won't need to manage the paperwork yourself. Your installer will typically help identify the right process and submit the necessary information.
Change to Choosing the right installer means expert support with your DNO application, from identifying the correct process to submitting the paperwork for you.
What is a DNO application?
A DNO application is a request to your local Distribution Network Operator (DNO) to connect an electricity-generating system, such as solar panels, or certain other electrical equipment to the local electricity network. Depending on the system size and complexity, the process may involve applying for approval before installation or notifying the DNO after installation.
Your DNO is responsible for operating and maintaining the electricity cables, substations and other infrastructure that deliver power to your property. It is different from your energy supplier, which is the company you pay for your electricity.
When you install solar panels or battery storage, your equipment can change how electricity flows between your property and the local grid. The DNO needs to understand this so it can check that the local network can operate safely and reliably.
The process helps the DNO assess whether your proposed system can connect as planned, whether any restrictions are needed, and whether network upgrades may be required.
Do I need a DNO application for solar panels or a battery?
In most cases, your solar or battery installation will need to be registered with your DNO. The exact process depends on the equipment, its electrical capacity, how it connects to the network and whether it can export electricity.
For smaller systems, your installer may be able to install the equipment and notify the DNO afterwards. Larger systems, particularly commercial ones, generally need approval before they are installed or connected.
You may also need to involve your DNO when:
-
Adding battery storage to an existing solar installation
-
Upgrading an inverter
-
Changing the amount of electricity your system can export
It's worth checking the requirements early. Finding out that your proposed system needs additional approval after you've agreed the design can cause avoidable delays.
G98 vs G99 vs G100 - what is the difference?
G98, G99 and G100 are technical requirements used in Great Britain to manage the safe connection of generation equipment and export-limiting systems to the electricity network.
The route that applies to your installation depends on the system's technical details, not simply whether it's a home or business installation.
G98: smaller generation systems
G98 generally applies to smaller, type-tested generation systems with a registered capacity of up to 16 amps per phase. On a typical single-phase supply, this is equivalent to 3.68kW.
This is often the route for smaller domestic solar installations.
Where the system qualifies for G98, it can usually be installed without waiting for prior DNO approval, provided the relevant requirements are met. The DNO must then be notified within 28 days of commissioning.
Your installer should confirm that the equipment and installation meet the G98 requirements before proceeding.
G99: larger or more complex systems
G99 generally applies to generation systems that fall outside the G98 criteria, including systems with a registered capacity above 16 amps per phase.
This is particularly relevant to commercial solar installations, larger domestic systems and some installations involving battery storage.
Unlike a qualifying G98 installation, a G99 system normally requires the DNO's approval before the relevant equipment is installed or connected. The DNO assesses the proposed system and may approve it as designed, impose conditions or request changes.
For businesses planning rooftop solar, battery storage or an expansion to an existing system, this can be a key part of project planning. The proposed capacity, existing electrical supply and local network conditions can all affect the outcome.
Important note: A battery does not automatically mean every installation follows the same G99 process. The correct route depends on the complete system design, equipment and applicable technical requirements.
G100: limiting electricity exports
G100 relates to systems that limit the amount of electricity exported to the network.
For example, a business might have a solar system capable of generating 100kW but be permitted to export only 60kW. A suitable export-limitation scheme can help keep exports within the agreed limit, while the business uses or stores more of its generated electricity on site.
An export limit may be part of the DNO's connection offer where the local network cannot accommodate the full proposed export. The technical design and control arrangements must meet the relevant requirements.
For commercial sites, understanding export limits early can help inform the choice of solar inverter, battery capacity and energy management system.
How does the DNO application process work?
The process varies by system, but a typical solar or battery project follows three main steps:
1. Your installer assesses the proposed system
Your installer assesses your system, identifies the correct DNO process and gathers the required technical information, including equipment specifications and electrical details.
2. The DNO reviews the proposal
The DNO checks whether the proposed system can connect safely. It may approve the design, set export limits, request further information or require network upgrades.
3. The installation is completed and registered
Once the relevant approval is in place, your installation can proceed. For systems that qualify for notification after installation, your installer will submit the required information within the applicable timeframe and provide you with the relevant paperwork.
How long does a DNO application take?
There isn't one timescale that applies to every DNO application.
DNO application timescales depend on your system, the type of application and your local network operator.
Qualifying G98 installations can generally be installed before notification is submitted, whereas G99 applications typically require approval in advance. G99 applications can take several weeks or longer, particularly if further information or network upgrades are needed.
If you're planning a solar installation, it's worth confirming DNO requirements early to avoid delays to your project.
What information is needed for a DNO application?
Your installer will usually prepare the application using details about your property and proposed system. This may include:
-
Property address and existing electricity connection details
-
Solar system capacity and equipment specifications
-
Inverter and battery details
-
Electrical drawings and connection details
-
Proposed export capacity and export-limitation equipment
-
Existing generation or storage at the site
-
Larger commercial installations may require additional technical information.
What happens if the DNO limits your solar system?
A DNO may approve your connection with an export limit or other conditions, or require network upgrades before your system can connect. This doesn't necessarily mean solar isn't viable, but your system design and financial savings may need to reflect those restrictions.
You may be able to make better use of your generation by increasing on-site electricity use, adding battery storage or using energy management systems. Your installer can advise on the options available, but any changes must comply with your DNO's agreed conditions.
Can I increase my export capacity later?
Potentially. If your DNO has imposed an export limit, you or your installer may be able to submit a revised application in future.
Whether a higher export capacity is approved depends on the network conditions at the time, the proposed system and any work required to support the change. Approval is not guaranteed, and additional costs may apply.
For businesses planning to expand their solar array or add batteries later, it is worth discussing future requirements during the initial design. A phased approach may be possible, but it should be based on the site's electrical infrastructure and the DNO's requirements.
How do I find my DNO?
Your DNO is determined by the location of your property or business site, not by your electricity supplier.
The easiest way to identify your network operator is to use the Energy Networks Association's online Who is my network operator? tool. Enter your postcode to find the relevant operator and its contact details.
If you're planning an installation, your solar installer should also be able to identify the correct DNO and explain which process applies.
The connection arrangements can differ in Northern Ireland, so check the relevant local network requirements if your property is there.
Do I need to submit the DNO application myself?
Usually, your installer will manage the technical paperwork and submit the relevant application or notification on your behalf.
However, it is important to confirm that the process has been completed correctly. The responsibility to comply with the applicable connection requirements does not simply disappear because an installer is handling the paperwork.
Here are some useful questions to ask your installer before your project begins:
-
Which DNO process applies to my installation?
-
Does approval need to be received before installation?
-
Are any export limits or connection conditions expected?
-
Could the application affect the project timeline or cost?
-
Will I receive confirmation and copies of the relevant documentation?
For a commercial installation, these questions should be part of the wider project planning process.
What does a DNO application mean for homeowners and businesses?
The requirements are the same in principle for homes and businesses, but the complexity can differ depending on system size, electrical capacity and export requirements.
For homeowners
Most domestic installations follow a relatively straightforward process. Your installer can confirm whether your system falls under G98 or requires G99 approval, and whether any restrictions apply.
For businesses
Commercial solar and battery installations may require more detailed assessments and can be affected by export limits, network capacity and connection costs. Considering DNO requirements early can help businesses plan their system, costs and expected savings more accurately.
Frequently asked questions about DNO applications
Is a DNO application the same as planning permission?
No. A DNO application covers connecting equipment to the electricity network. Planning permission is separate and may also be required depending on your property and installation.
Can I install solar panels before my DNO application is approved?
It depends on your system. Qualifying G98 installations can generally be installed and notified afterwards, while G99 installations typically require prior approval.
Does adding a battery mean I need a new DNO application?
Possibly. Adding a battery can change how electricity flows through your system, so your installer should check whether an updated application or notification is needed.
Does a DNO application guarantee that I can export all my surplus solar electricity?
No. The DNO may approve the connection with an export limit or other conditions. The amount of surplus solar electricity you can export depends on the approved connection arrangements and any required control equipment.
Can my DNO application be rejected?
The DNO may request changes, impose conditions or require network upgrades instead of approving your proposal as submitted.
Does a DNO application cost money?
Costs vary depending on the application, technical requirements and whether network upgrades are needed. Check with your installer whether DNO fees are included in your quote.
Planning solar for your home or business? Plug me in can help
A DNO application might sound complicated, but with the right solar installer, it can be a smooth and straightforward part of your project.
At Plug me in, we've spent more than 15 years helping homeowners and businesses across the UK make the switch to solar.
Whether you're considering solar for your home or planning a larger commercial installation, we're here to help you understand the process and take the next step with confidence.